| 1. | To add a task to a baseline or interim plan 如果要将任务添加到比较基准或中期计划: |
| 2. | Add a task to a baseline or interim plan 将任务添加到比较基准或中期计划 |
| 3. | To set an interim plan 如果要设置中期计划: |
| 4. | To add the task to the interim plan , click save interim plan 如果要将任务添加到中期计划,请选择“保存为中期计划”选项。 |
| 5. | Set an interim plan 设置中期计划 |
| 6. | An interim plan is a set of schedule information you can save at any time during your project 中期计划就是在项目过程中随时保存的日程信息的集合。 |
| 7. | 2 . in the task name field , select the task you want to add to the baseline or interim plan 2 。在“任务名称”域中,选择要添加到比较基准或中期计划中的任务。 |
| 8. | You can compare an interim plan with the baseline plan to monitor project progress or slippage 可以将中期计划和比较基准计划进行比较,以监视项目进度或落后情况。 |
| 9. | You can compare the information in an interim plan with baseline information to monitor project progress 您可以将中期计划中的信息同比较基准信息进行比较,以监视项目进度。 |
| 10. | After you save a baseline plan and begin updating your schedule , you may want to periodically save an interim plan 保存比较基准计划并开始更新日程之后,或许需要定期保存中期计划。 |