钟表装置 meaning in Chinese
clockwork
Examples
- You can fine - tune task links - and make sure you do n ' t gum up the clockwork - by using lag time and lead time
使用“前置重叠时间”和“延隔时间”调整任务链接,并且确保那些钟表装置不会粘上油漆。 - For example , in the clockwork project , painting the walls precedes hanging the clocks , and those tasks have a finish - to - start link
譬如,在钟表装置展览项目中, “粉刷墙壁”任务位于“悬挂钟表”任务的前面,并且这些任务具有完成-开始链接。 - For example , in preparation for a clockwork exhibit , the tasks " painting the walls , " " hanging clocks , " and " arranging furniture " are scheduled for monday , tuesday , and wednesday , respectively
譬如,在钟表装置展览的准备工作中, “粉刷墙壁” 、 “悬挂钟表”和“布置家具”三项任务分别安排在周一、周二和周三。 - For example , the planner for the clockwork exhibit knows that the museum work crew won ' t be available to paint the gallery walls until january 28 , so the planner specifies that painting start no earlier than january 28
譬如,钟表装置展览会的规划者得知博物馆工作人员在1月28日之前无法粉刷陈列室墙壁,则规划者指定粉刷工作不得早于1月28日开始。 - For example , a clockwork exhibit crew will hang the clocks only after painting the walls . the task of hanging clocks is linked to the task of painting walls , because the start date for hanging clocks can occur only after the finish date for painting walls
譬如:钟表装置展览会的工作人员只有在粉刷墙壁之后才能悬挂钟表, “悬挂钟表”的任务必须与“粉刷墙壁”的任务相链接,因为“悬挂钟表”的开始日期只能发生在“粉刷墙壁”的完成日期之后。