- Flood prediction scheme and flood control countermeasure for nanliujiang river
南流江洪水预报方案与防洪减灾对策 - Combined with the significant project - gongboxia hydro - power station construction , emphasized on construction during flood period of power station construction period , the climate character of the upstream of yellow river basin and the practice operation state of cascade reservoirs are analyzed , some problems in construction during flood period such as flood propagation time , interval flood discharge forecast , construction risk , flood period pre - alarm and longyangxia reservoir ' s function on construction of gongboxia are also studied , with an aim at presenting real interval flood forecast scheme and dispatching method , so as to provide technological support for gongboxia hydro - power station construction period
本论文结合国家重点工程项目?公伯峡水电站的建设,以电站建设期施工渡汛为研究重点,从实施出发,分析黄河上游气候特性和梯级水库群的实际运行状况,对施工渡汛中的主要问题?洪水流达时间、区间洪水预报、渡汛风险、汛期预警、龙羊峡水库在渡汛中的作用等进行了比较全面深入的研究,目的在于提出可用于实际的区间洪水预报方案和调度方法,为公伯峡水电站施工期建设提供技术支撑。